Read the latest ARM customer risk management case study.

Skanska won the award for “Outstanding Contribution to the Risk Industry” for its pro-active risk management on the M25 London orbital road widening project. Read our latest case study to discover why their project was judged the best in the business and find out how Active Risk Manager underpinned the successful on-budget, on-time delivery of this time-critical project.

 

The Challenge: Deliver improvements to London’s orbital road infrastructure before the London 2012 Olympics or face £70m ($113m) in costs and liquidated damages

 

The Solution: Implement ARM Enterprise Risk Management software rather than hold risk registers in multiple spreadsheets

 

The Results: Project completed 8 weeks ahead of schedule and wins several risk management awards

 

Click here to read the full case study.

Leave a Response

*
*

(1) Response to “Risk Management Case Study: Skanska”

  1. Shanka HN says:

    I teach PRM for MBA students specialising in Project Management. Of interest is the fact I lived in Milton Keynes for a year and half and used the M25 to travel to Gatwick.

    I am interested in this case study to understand the issues and problem that surfaced, how the Project Risk was managed and net effect it has on th overall project.
    Thanks You
    Prof. HN Shankar